Distribution Rates | ||
Residential | ||
Service Charge | $ 39.29 | |
Smart Metering Entity Charge - effective until December 31, 2022 | $ 0.57 | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.17 | |
Distribution Volumetric Rate | $ 0.0057 /kWh | |
Low Voltage Service Rate | $ 0.0025 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0016 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($0.0011) /kWh | |
General Service <50 kW | ||
Service Charge | $ 42.03 | |
Smart Metering Entity Charge - effective until December 31, 2022 | $ 0.57 | |
Distribution Volumetric Rate | $ 0.0101 /kWh | |
Low Voltage Service Rate | $ 0.0024 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0016 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($0.0011) /kWh | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0002 /kWh | |
General Service >50 kW | ||
Service Charge | $ 214.93 | |
Distribution Volumetric Rate | $ 4.3555 /kW | |
Low Voltage Service Rate | $ 1.3285 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.5644 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($ 0.4027) /kW | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0766 /kW | |
Unmetered Scattered Loads | ||
Service Charge (per connection) | $ 13.01 | |
Distribution Volumetric Rate | $ 0.0218 /kWh | |
Low Voltage Service Rate | $ 0.0024 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0019 /kWh | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($0.0011) /kWh | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0002 /kWh | |
Sentinel Lights | ||
Service Charge (per connection) | $ 13.71 | |
Distribution Volumetric Rate | $ 62.4624 /kW | |
Low Voltage Service Rate | $ 1.0383 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.4703 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($ 0.4019) /kW | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0764 /kW | |
Street Lighting | ||
Service Charge (per connection) | $ 4.19 | |
Distribution Volumetric Rate | $ 28.9614 /kW | |
Low Voltage Service Rate | $ 0.7003 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.5991 /kW | |
Rate Rider for Disposition of Deferral/Variance Accounts (2017) - effective until April 30, 2020 - Applicable only for Non-Wholesale Market Participants | ($ 0.3919) /kW | |
Rate Rider for Disposition of Group 2 Deferral/Variance Accounts (2017) - effective until April 30, 2020 | $ 0.0745 /kW | |
microFIT Generator | ||
Service Charge | $ 5.40 | |
Specific Service Charges | ||
Customer Administration | ||
Arrears Certificate | $15.00 | |
Easement Letter | $15.00 | |
Credit reference/credit check (plus credit agency costs) | $15.00 | |
Account setup/change occupancy charge (plus credit agency costs if applicable) | $30.00 | |
Returned Cheque (plus bank charges) | $15.00 | |
Meter dispute charge plus Measurement Canada fees (if meter found correct) | $30.00 | |
Non-Payment of Account | ||
Late Payment - per month | 1.50% | |
Late Payment - per annum | 19.56% | |
Collection of account charge - no disconnection | $ 15.00 | |
Collection of account charge - no disconnection - after regular hours | $ 165.00 | |
Reconnect at Meter - during regular hours | $ 65.00 | |
Reconnect at Meter - after regular hours | $ 185.00 | |
Reconnect at Pole - during regular hours | $ 185.00 | |
Reconnect at Pole - after regular hours | $ 415.00 | |
Install/Remove load control device - during regular hours | $ 40.00 | |
Install/Remove load control device - after regular hours | $ 185.00 | |
Other | ||
Special Meter Reads | $ 30.00 | |
Temporary service install and remove - overhead - no transformer | $ 632.00 | |
Temporary service install and remove - underground - no transformer | $ 468.00 | |
Temporary service install and remove - overhead - with transformer | $ 2525.00 | |
Specific Charge for Access to the Power Poles - per pole/year | $ 43.63 | |
Allowances | ||
Transformer Allowance for Ownership - per kW of billing demand/month | ($ 0.60) /kW | |
Primary Metering Allowance for transformer losses - applied to measured demand and energy | (1.00)% | |
Billing Determinant | ||
The billing determinant is the customer’s metered energy consumption adjusted by the Total Loss Factor as approved by the Board and set out in this Schedule of Other Regulated Rates. | ||
Loss Factors | ||
Total Loss Factor - Secondary Metered Customer < 5,000 kW | 1.0604 | |
Total Loss Factor - Primary Metered Customer < 5,000 kW | 1.0498 | |
Retail Transmission Rates | ||
Residential | Network Service Rate | $ 0.0057 /kWh |
Line and Transmission Connection Service Rate | $ 0.0040 /kWh | |
General Service <50 kW | Network Service Rate | $ 0.0052 /kWh |
Line and Transmission Connection Service Rate | $ 0.0037 /kWh | |
General Service 50 to 4999 kW with no interval meter | Network Service Rate | $ 2.0227 / kW |
Line and Transmission Connection Service Rate | $ 2.0940 /kW | |
General Service 50 to 4999 kW with an interval meter | Network Service Rate | $ 2.0227 / kW |
Line and Transmission Connection Service Rate | $ 1.9620 / kW | |
Sentinel Lighting | Network Service Rate | $ 1.5830 / kW |
Line and Transmission Connection Service Rate | $ 1.6365 / kW | |
Street Lighting | Network Service Rate | $ 1.5750 / kW |
Line and Transmission Connection Service Rate | $ 1.1038 / kW | |
Unmetered Scattered Load | Network Service Rate | $ 0.0052 /kWh |
Line and Transmission Connection Server Rate | $ 0.0037 /kWh | |
Other Regulated Rates | ||
Wholesale Market Service Rate (WMS) - not including CBR | $ 0.0032 /kWh | |
Capacity Based Recovery (CBR) - Applicable for Class B Customers | $ 0.0004 /kWh | |
Rural or Remote Electricity Rate Protection Charge (RRRP) | $ 0.0003 /kWh | |
Standard Supply Service – Administrative Charge (if applicable) | $ 0.25 | |
Electricity Commodity Rate | ||
Residential | ||
Effective May 1, 2018 | ||
Time-of-use pricing | On-peak | $ 0.1320 /kWh |
Mid-peak | $ 0.0940 /kWh | |
Off-peak | $ 0.0650 /kWh | |
Tiered pricing | 1st 600 kWh | $ 0.0770 /kWh |
Balance | $ 0.0890 /kWh | |
General Service <50 kW and Designated | ||
Effective May 1, 2018 | ||
Time-of-use pricing | On-peak | $ 0.1320 /kWh |
Mid-peak | $ 0.0940 /kWh | |
Off-peak | $ 0.0650 /kWh | |
Tiered pricing | 1st 750 kWh | $ 0.0770 /kWh |
Balance | $ 0.0890 /kWh | |
General Service >50 kW and >250,000 kWh, without interval meter | ||
Weighted Average Hourly Ontario Electricity Spot | Market Price | |
General Service >50 kW and >250,000 kWh, with interval meter | ||
Hourly Ontario Electricity Spot | Market Price | |
Sentinel Lighting | ||
Effective May 1, 2018 | 1st 750 kWh | $ 0.0770 /kWh |
Balance | $ 0.0890 /kWh | |
General Service Unmetered | ||
Effective May 1, 2018 | 1st 750 kWh | $ 0.0770 /kWh |
Balance | $ 0.0890 /kWh |