Project Status - Scheduled

Ward/Councillor:

Ward 1 - Councillor Kevin Eisses

Title:

Innisfil Beach Road Hwy 400 Pole Relocation

Brief Description:

InnPower will be relocating the existing Hydro Lines crossing Highway 400 at Innisfil Beach Road.

Detailed Description:

InnPower is working in conjunction with Ministry of Transportation to relocate the existing overhead distribution lines crossing Highway 400 along Innisfil Beach Road to accommodate upcoming road construction. This work will include the installation of approximately 15 hydro poles on the South side of Innisfil Beach Road and the removal of the existing infrastructure on the North side.

Construction is expected to begin in the middle to end of August and will last for approximately 11 weeks. Commercial customers in the area may be impacted by this construction. Outages has a result of construction work are only done out of necessity and are always kept to a minimum. Any customers that will be affected by a planned outage will be notified at least 5 days in advance.

If you have any questions, please feel free to reach out to Customer Service at (705) 431-4321 or cs@innpower.ca. We can also be reached on Twitter and Facebook. The Engineering Technician for this construction project, Tyler Swanton, can be reached via email at tylers@innpower.ca or by cellphone at (249) 535-0012.